Dismantling of reinforced concrete structures in Khmelnytskyi region

Address: Ukraine, Khmelnytskyi region
General Contractor:
Dates: 2026
Project Scope: dismantling 1200 m³ of high-strength reinforced concrete, destruction of massive silo structures, working in a confined space, ensuring the efficiency of equipment with high-strength concrete, meeting deadlines, organizing safe material movement, complete cleaning of the territory.

General characteristics of the object

The Tereshchenko Group of Companies completed a complex project to dismantle industrial reinforced concrete structures on the territory of a production complex in the Khmelnytskyi region. The object was a massive silo structure that had been operated for a long time under significant static and dynamic loads.

Such structures are built using high-strength concrete with a high cement content and dense reinforcement. The thickness of the walls and load-bearing elements in such objects significantly exceeds standard construction indicators, which significantly complicates the dismantling process.

Main challenges of the project

The key difficulty was the exceptional strength of the reinforced concrete used in the construction of the object. The structures had:

  • high concrete density;
  • multi-level reinforcement;
  • a ​​significant thickness of the load-bearing walls;
  • complex geometry of the silo elements.

An additional factor of complexity was the need to perform work within the existing industrial infrastructure, which required clear coordination of equipment and compliance with increased safety standards.

Work execution technology

To achieve maximum efficiency, a phased dismantling technology was used:

1. Preparatory stage
An assessment of the technical condition of the structures was carried out, zones of increased strength were identified, and an optimal dismantling sequence was formed.

2. Primary destruction
Massive structural elements were subjected to intensive destruction using a hydraulic hammer, which allowed the reinforced concrete to be exposed and its integrity to be reduced.

3. Mechanical dismantling
After the structures were weakened, phased dismantling of large fragments was carried out with their subsequent crushing to transportable sizes.

4. Sorting and moving material
The dismantled reinforced concrete was divided into fractions suitable for further removal or processing.

5. Cleaning the area
After the completion of the main works, the site was completely cleaned of construction debris and structural remains.

Features of the work

  • The work was carried out in conditions of limited space between industrial buildings.
  • Heavy-duty and powerful equipment was used to work with high-strength concrete.
  • Constant stability of the residual structures was ensured during dismantling.
  • All safety requirements were observed when working with heavy equipment and high-rise elements.

Project result

1,200 m³ of high-strength reinforced concrete was successfully dismantled within the project. The work was completed within the established deadlines without emergencies and in compliance with all technological standards.

The Tereshchenko Group of Companies once again confirmed its expertise in the field of complex industrial dismantling, ensuring an effective combination of technical solutions, team experience and modern equipment.

LOOKING FOR A RELIABLE EXPERT FOR YOUR NEXT PROJECT?

Equipment used for the project:

High productivity and quality of work were made possible by the use of modern special equipment:

Excavators:
Volvo EC 220 DL. Used for auxiliary work, including clearing the territory, forming work areas and moving leftover materials.
SANY SY365C. Used for dismantling large structural elements, moving massive fragments and loading dismantled material.
HYUNDAI R330LC-9S. Used as the main base for installing a hydraulic hammer and performing work on the destruction of the strongest sections of reinforced concrete structures.

Attachments for excavators:
HANWOO pulverizer. Used for crushing already destroyed reinforced concrete and effectively separating reinforcement from concrete.
SOOSAN SB140 hydraulic hammer. Used for intensive crushing of high-strength concrete, destruction of thick-walled elements and opening reinforced areas.

HOW TO ORDER A SERVICE?

The Tereshchenko Group strives to ensure the most convenient communication for our clients. You can contact us in any way that is convenient for you:

  • Call us: 0503531188
  • Write or call us via Viber: 0662154248
  • Send us an e-mail: 1725577@gmail.com
  • Or fill out the feedback form and we will get back to you!

LOOKING FOR A RELIABLE EXPERT FOR YOUR NEXT PROJECT?

near_meOur Address

Ukraine, Kyiv
Antonovycha Street 56,
APK EV Building, Office 404

mailAlways Online

1725577@gmail.com
demontazh-group.com

phoneAlways in Touch

Phone: +380503531188
Viber: +380662154248

watchWorking Hours

Mon–Fri: 9:00 – 18:00
Sat: 11:00 – 17:00
Sun: By Appointment