Our first project in 2023 not related to the war…
For the construction of a new bio-fertilizer plant in the Cherkasy region, a set of demolition and preparatory works had to be carried out.
The Tereshchenko Group of Companies was set two tasks:
1. Demolition of old warehouse premises and removal of construction debris.
2. Excavation for the construction of the plant.
All works were completed within 10 days.
Demolition: 4,000 m³ (of building volume)
Excavation: 7,000 m³
The following was used to carry out the works:
Excavators:
– Excavator HYUNDAI R330LC-9S
– Excavators Volvo EC 220 DL
Attachments:
Hydraulic shears NPK S-22XA
Hydraulic shears Rent Demolition RD15
Dump trucks:
Four-axle dump truck SCANIA P400 8X4
Four-axle dump truck VOLVO FM400 8X4