The Tereshchenko Group of Companies continues to take part in the most important projects for the reconstruction of Ukraine. For most of them we cannot disclose information for obvious reasons…
As part of the work at one of our sites, we carried out the demolition of various types of structures and constructions:
– reinforced concrete buildings;
– brick buildings;
– reinforced concrete foundations;
– other concrete structures.
During wartime, our team faces new challenges, since a large amount of unexploded ordnance remains scattered across the whole territory of Ukraine. But despite this, work at all sites continues to be carried out on time!
Our experienced specialists have developed working methods that make it possible to minimize risks while carrying out the works.
The total volume of demolition works of all levels of complexity amounted to 22,000 m3. In addition, works were carried out to remove large foundation elements, backfill roads, process construction waste after demolition, as well as sort and transport construction waste.