The specialists of TERESHCHENKO Group carried out the demolition of a bomb shelter and adjacent premises on the grounds of Okhmatdyt Children’s Hospital – one of Ukraine’s leading medical institutions.
The site is located in the city centre, so the works demanded exceptional precision, care and control at every stage. In a dense urban setting, right next to operating hospital buildings, it was essential not only to get the job done but also to guarantee absolute safety for staff and equipment.
Objectives
Our specialists were tasked with the following:
- carry out the demolition of the reinforced concrete structures of the bomb shelter and adjacent premises;
- ensure complete safety of the works in an area crowded with underground utilities;
- deliver the project without hydraulic breakers, so as not to induce vibration;
- maintain the stability of adjacent structures and avoid any impact on sensitive high-tech medical equipment;
- complete the works within a strict deadline with no compromise on quality.
Work sequence
The demolition works were carried out at depths of up to 7 metres, which made the process considerably more complex.
The total volume of demolished structures was approximately 700 m³ of reinforced concrete – a modest volume compared with large-scale projects, but one that demanded the utmost precision.
The main challenges were the thick bomb shelter roof slab (up to 700 mm) and the large number of buried utilities.
As the use of a hydraulic breaker was ruled out because of the risk of damaging hospital equipment, our specialists used a non-percussive demolition method – a low-noise technique that generates no vibration and allows work in environments highly sensitive to external impacts.
This method was delivered using specialist machinery with precise force control and manual finishing of structural elements, ensuring a high degree of accuracy even in the most difficult areas.
Result
The works were completed:
- in full and on time,
- in accordance with the client’s technical specification,
- without breaching safety requirements or disrupting the operation of medical equipment.
Thanks to the experience of our engineers, a well-coordinated team and modern methods, the project was delivered without noise, vibration or a single incident.
The site is fully prepared for further construction, and the trust of a client such as Okhmatdyt has confirmed the company’s strong reputation in technically complex demolition.
Non-percussive demolition
Non-percussive demolition breaks down concrete and reinforced concrete structures without heavy mechanical impact. It reduces noise, vibration and the risk of damage to neighbouring buildings or equipment, which makes it ideal for densely built-up areas and sensitive facilities such as hospitals.
A professional approach
The team included engineers, plant operators, specialist machinery operators and technical supervision staff.
Every stage was overseen by experienced site managers, ensuring precision and quality in even the smallest operations.
TERESHCHENKO Group professionally carries out demolition works of any complexity – from partial demolition to complete dismantling of structures.
We work where maximum precision, safety and accountability are required.
Get in touch – we will find a solution even where others will not take the risk.