Preparing the construction site required both full and partial demolition of buildings and foundations. Particular difficulty was posed by structures that had to be partially demolished without causing any damage to the remaining parts of the building.
Volume of demolition work — 5,800 m³
The project employed a VOLVO EC 220DL excavator and a JCB 220 excavator fitted with SOOSAN SB 70 hydraulic breakers, along with SCANIA P400 and VOLVO FM 400 dump trucks.