At the Ascania-Flora site, the TERESHCHENKO Group team was tasked with processing and crushing construction materials after demolition. The job involved recycling reinforced concrete structures and brick with a total volume of over 2,500 m³.
Purpose of the works – to produce recycled aggregate for reuse in subsequent construction and road works, reducing the client’s spending on virgin materials and minimising construction waste.
Work sequence
- Preparation: sorting and stockpiling of construction debris – reinforced concrete slabs, structural fragments and brick.
- Crushing: feeding the material into a mobile crushing and screening plant, which reduces it to the required fraction size.
- Processing: separating steel from concrete, screening the aggregate and preparing it for reuse.
- Final result: high-quality recycled aggregate suitable for road bases, industrial hardstandings and other construction applications.
Result
- Recycled: 2,500 m³ of reinforced concrete and brick.
- A substantial volume of recycled aggregate was produced for reuse.
- The client achieved budget savings by reducing the need for virgin materials.
- Environmental impact was reduced through lower waste volumes.
Benefits for the client
The work of TERESHCHENKO Group not only cleared the site but also produced a valuable construction resource, ready for reuse. It is a clear example of an integrated approach, where demolition and recycling become a cost-effective and environmentally sound solution.