We carried out a large-scale package of demolition works to clear the site for a new plant for Astarta Agro Protein LLC. The job called for specialist machinery, including a jaw crusher, excavators fitted with hydraulic breakers and shears, and heavy tipper trucks. Thanks to a well-coordinated team and high-performance equipment, every stage of the demolition was completed safely and to a high standard.
Scope of works:
- Demolition of production buildings
The project included the complete demolition of the production buildings, covering both external and internal structures, which required highly skilled operatives and specialist machinery.
- Foundation demolition
The foundations were broken out by heavy excavators fitted with hydraulic breakers, allowing the concrete bases of the buildings to be removed quickly and efficiently and the site to be made ready for new construction.
- Bomb shelter demolition
One of the most demanding stages was the demolition of a bomb shelter with a reinforced structure. The work was carried out in full compliance with safety requirements to prevent accidents and protect the environment.
- Basement demolition
Basement demolition called for particular care and precision. Our engineers carried out a detailed structural assessment before work began, which prevented any uncontrolled movement or damage to adjacent structures.
- Dismantling of steel grain silos and dryers – 700 t of steel
Steel grain silos and dryers with a total weight of 700 tonnes were dismantled. This required specialist equipment, in particular hydraulic shears, to cut down the large steel members efficiently.
- Dismantling of steel structures
A range of steel structures was dismantled, including building frames and other steel elements, using high-performance hydraulic shears.
- Concrete and brick recycling – 14,000 m³
All demolished concrete and brickwork was crushed on site with a McCloskey J40 jaw crusher. In total, 14,000 m³ of material was recycled into aggregate for subsequent construction works.