The positive trend in new plant construction and capacity expansion can be seen not only in western Ukraine, but also in the central and even northern regions of the country.
Our latest project is also located in the Poltava region. To expand capacity, install new equipment and erect new plant buildings, the client brought in TERESHCHENKO Group to carry out the following works:
— demolition of concrete supports;
— backfilling of a pond with recycled crushed aggregate;
— backfilling and compaction of soil;
— site levelling.
Using modern machinery, our experienced excavator operators broke out 32 concrete support foundations weighing 9 tonnes each. Once demolition was complete, the pond and the construction area were backfilled with 3,500 m³ of crushed aggregate, then levelled and compacted with a vibratory roller.